What is a Section 278 agreement?
Section 278 of the Highways Act 1980 allows a developer to enter into an agreement with the highway authority to carry out works on the existing public highway, or to fund the authority to carry them out. Think new junctions, roundabouts, traffic lights, road widening, pedestrian crossings or a new access onto a main road.
Why is it needed?
Where a new development affects the existing road network, planning permission is often granted on condition that highway improvements are delivered. Because the land is already public highway, a developer can’t simply start work. The highway authority needs to control the design, safety and quality of the works, and a Section 278 agreement gives it the legal framework to do so.
How does it differ from Section 38?
It’s easy to mix them up:
- Section 38 covers new roads built within your development that are then adopted.
- Section 278 covers works to existing public highway outside or at the edge of your site.
Many schemes need both: a Section 278 for the junction onto the main road, and a Section 38 for the estate roads behind it.
Why is a bond needed?
Works on live roads carry real risk, and an unfinished junction is a safety and traffic problem for the whole community. Authorities typically require a bond so that funds are available to complete or correct the works if the developer can’t.
How Advantage can help
Advantage provides insurance-based bonds for Section 278 obligations alongside Section 38 and Section 104. That means one specialist partner for the bonds your development needs, and cash that stays in your business rather than being held as security.
Speak to the team at www.ahci.co.uk to discuss your requirements.